Chapter 3 · Phase 7

I.

✓ Complete

Plan

Your vision becomes buildable paper.

II.

✓ Complete

Prep

Permits, people, parts.

III.

You are here

Build

The pool takes shape in your yard.

IV.

Ahead

Finish

From bare shell to first swim.

Current phase

Excavation

Breaking ground. The pool's shape appears in your yard.

Document your build

3 photos on file. Snap another anytime.

Video guide

Phase guide

Excavation — from first bucket to final grade

12:48

My notes

The short of it

Full guide · 12:48

Tuesday morning around 7 AM, Desert Dig Co. rolls in with a mini-excavator and a haul-off trailer. The first hour is all layout — Miguel walks your staked outline, double-checks elevations against the plan set, and confirms where the spoil pile lands so it doesn't block the rest of the build.

Expect two to three days of dig. Day one carves the gross shape and shelf. Day two squares up the steps, benches, and any raised spa footprint. Day three is for cleanup, grading, and the inspection pre-check — this is also when the site feels real for the first time.

Your job during the phase: stay reachable, cover patio furniture from dust, and clear the driveway the night before so the crew can stage. The checklist on the right covers the exact pre-dig items — tick each off before Tuesday and you'll have a clean, fast dig.

Wrap this phase

Mark Excavation complete when you're ready.

You have 4 items left — you can still mark it complete and come back later.

Just behind · Phase 6

Equipment Ordering

Completed Apr 3Review